Edwards Aquifer Recharge Modeling

Client: Edwards Aquifer Authority, San Antonio, TX and U.S. Army Corps of Engineers, Fort Worth, TX

Clear Creek Solutions provided hydrologic modeling services to the Edwards Aquifer Authority of San Antonio, Texas including:

  • Computation of recharge to the Edwards Aquifer.
  • Comparison of recharge estimates based on different precipitation data sources.
  • Reviewing and analyzing results.
  • Creating a Windows-version of HSPF for the nine major basins that cross the Edwards Aquifer.

Process and Solution

Comparative analyses were made to determine the preferred precipitation data set for the model.

The comparative analyses focused on the computation of recharge using the National Weather Service (NWS) precipitation data as well as the NEXRAD radar data.

For the NWS data, we augmented precipitation with the Authority's Real-Time Network hourly precipitation data where needed

Result

The evaluation of the analyses found that the NWS hourly precipitation data produced more accurate simulated streamflow data. In turn, this produced more accurate recharge estimates than the NEXRAD daily precipitation data.

Clear Creek Solutions also trained the Edwards Aquifer Authority staff on how to use HSPF hydrology and hydraulics software.

This information assisted Authority staff in the evaluation of alternative solutions to increase groundwater recharge.

Our Projects

Land Development Stormwater Analysis
Land Development Stormwater Analysis

A private client contracted with Clear Creek Solutions to investigate potential downstream flooding in conjunction with a proposed land development in Western Washington. The development will be constructed to provide direct discharge from the project site through a tide gate to Puget Sound.

Government Canal Stormwater Analysis Study
Government Canal Stormwater Analysis Study

The City of Pacific contracted Clear Creek Solutions as the stormwater modeling subconsultant to find a pump solution to alleviate flooding in and around the Government Canal.

Monte Villa Parkway Drainage Study
Monte Villa Parkway Drainage Study

The City of Bothell contracted Clear Creek Solutions to investigate the observed street and private property drainage problems along 35th Avenue SE between 228th Street SE and 240th Street SE and south of 240th Street SE to Monte Villa Parkway.

Yauger Park Regional Stormwater Facility Expansion
Yauger Park Regional Stormwater Facility Expansion

Clear Creek Solutions (CCS) and Davido Consulting Group (DCG) were selected by the City of Olympia to assist in the proposed expansion of a joint-use recreation and stormwater flow control facility.

Hydrologic And Hydraulic Modeling Of The Yauger Park Drainage Basin
Hydrologic And Hydraulic Modeling Of The Yauger Park Drainage Basin

The City of Olympia contracted with Clear Creek Solutions to provide hydrologic and hydraulic modeling services. Our solutions were successful in reducing flooding in the Yauger Park drainage system caused by large events like the December 2007 flood.

Edwards Aquifer Recharge Modeling
Edwards Aquifer Recharge Modeling

Comparative analyses were made to determine the preferred precipitation data set for the model.

Costco Stormwater Facility Sizing
Costco Stormwater Facility Sizing

Costco's development of a new store in south Snohomish County, just north of Woodinville, required innovative strategies and analysis to protect adjacent Little Bear Creek.

HSPF Watershed Calibration Clark County, WA
HSPF Watershed Calibration Clark County, WA

Clark County contracted with Otak to update the County's stormwater ordinance. Clear Creek Solutions was hired to produce HSPF calibrations of two watersheds in the county.

Olympia Sea Level Rise Modeling
Olympia Sea Level Rise Modeling

Clear Creek Solutions constructed a WWHM-SWMM model of the City of Olympia drainage systems impacted by a rise in sea levels and associated Puget Sound high tides.